Saturday, January 2, 2016

December XP-82 Twin Mustang Restoration Project Update



Another year has gone by so quickly.

But looking back at all the pictures that were taken in 

December 2014, a tremendous amount has been accomplished.

Center Section Leading Edge Assembly
This leading edge sub-assembly has been completed for some time now, and two team members spent a week fitting it to the leading edge spar. This was a complex job as it had to fit around and in between all of the forward gear door up-lock mechanisms mounted on the forward spar. Also, the six gun ports had to be properly positioned in the leading edge skin to align with the .50 cal. gun barrel blast (cooling) tubes. The leading edge assembly must remain off to perform the preliminary adjustments of the gear door up-locks during the gear retraction tests. 


Leading edge being fit 
(notice the prop spinners on left-hand side of the center section)


Belly Scoops/Radiators/Coolant Header Tanks
The final two Dzus/nut plate panels that close out at and aft of the bottom of each radiator have now been completed. All four feed and return 2” coolant lines are now completed, along with the 1.25” intercooler lines.  



Both pressure relief valves, one each mounted on each coolant header tank, are now overhauled and installed.


Pressure relief valves for the coolant header tanks


Coolant header tank with one pressure relief valve installed

Special XP-82/P-51 Coolant Water Necks
These coolant water necks are peculiar to only the Merlin-powered XP-82 and P-51H engines. They were not included with the overhauled engines as they are considered part of the cooling system. With much searching Nixon Vintage V-12s (the facility in Tehachapi CA, that overhauled our two engines) came up with two pair of them. Thanks. They are now permanently installed on both engines.



Main water inlet to engine water pump installed


Water necks installed on the Merlin engine

Firewall Forward Jobs
The majority of the month of December has been taken up completing all of the miscellaneous must-be-completed FWF jobs. All of the feed and return vacuum lines from the vacuum pumps to each firewall and air/oil separators have now been completed. 

On the left-hand firewall, there is a pressure-controlling valve that controls the vacuum pump discharge pressure airflow through pilot-selected lines out to drop tanks mounted on both wings. This vacuum pump discharge pressure is used to pressurize each drop tank to push and transfer the fuel without the help of a fuel pump back through return lines to the 95-gallon inboard fuel tank, a unique design.  We had three of these valves that had been under water for countless years and fortunately, among all three valves, enough airworthy parts were recovered to restore one good valve. 


Two vacuum air/oil separators, two ignition starting boosters in their mounting boxes, two pre-oil solenoids and check valves, two tach generators and the two electric/mechanical carburetor air control mechanisms have now been permanently installed.


Air/oil vacuum separator


Starting ignition vibrator


Pre-oil solenoid


Carburetor air control mechanisms

Temperature Probes (Oil and Coolant), Chip Detectors & Drain Ports
On a number of the coolant and oil lines, temperature resistance probes are threaded into special welded fittings in each line. These electrical-resistance probes sense the coolant and oil temperatures and their ohms resistance is transmitted through DC wiring to the respective instrument in each cockpit to indicate the temperatures. Also on the lower point of a number of oil and glycol tubes, there are welded-in drain ports and, on each oil return line, there are chip detectors threaded into welded tube fittings.


Both entire FWF electrical harnesses have been final installed and attached using Adel clamps and wired in through Cannon plugs to numerous respective locations (generators, starters, tach generators, temperature probes, primers, chip lights, carb air temperature motor controls for induction air temperature, pre-oil, feather pumps, etc.).



Inboard Gear Doors
We have just started manufacturing our two inboard gear doors. These doors are exceptionally complex riveted and spot-welded assemblies. We recovered two extremely munched doors from the Alaska wreck site, not one part was usable. However, the damaged door parts are giving us a huge amount of information on how to manufacture all the new parts and how they go together.  

Completing these two complicated doors will take sometime; we will keep everyone updated on our progress. 




Happy New Year 
from
Tom, Allison and the 
XP-82 Twin Mustang Restoration Team

6 comments:

  1. I so look forward to your updates, thank you and happy new year!

    ReplyDelete
    Replies
    1. Thank you for your interest in this most unique and rare warbird.

      Delete
  2. The complexity of this project boggles the mind !

    Can you show a more overall view of the aircraft's current state each month so one could get a understanding of the overall progression ?


    Thanks !

    ReplyDelete
  3. Allison,
    Thanks for the tour today, it was great seeing the actual plane in person! You have a great crew there! Kudos to all!!! Can't wait to see it flying !!!

    Greg

    ReplyDelete